The proposed extension of the Expo Line is currently undergoing the environmental planning process. A Draft
EIS/EIR is anticipated to be available for public comment
in Fall 2008.
Community Meetings
Grade Crossing Determinations Community Meeting:
The Expo Phase 2 Team will present an update on the grade crossing determinations for both the Exposition Right-of-way and the Venice/Sepulveda alternatives at an upcoming community meeting (details below). We welcome your questions and input on the proposed Expo Line grade crossings at this important stage in the environmental process.
DATE
TIME
LOCATION
NOTICE
PRESENTATION
06/09/08
6:30pm
Vista del Mar Child and Family Services Gymnasium
3200 Motor Avenue
Los Angeles, CA 90034
Fact
Sheet
Project Overview
Phase 2 of the Expo Line project proposes to improve public transit service and mobility in the Exposition Corridor by extending the benefits of Expo Phase 1 (under construction) beyond its currently planned terminus in Culver City to a terminus in Santa Monica. Phase 2 is undergoing the Alternatives Analysis (AA) process and the development of an Environmental Impact Statement (EIS) and Environmental Impact Report (EIR).
Initial Screening Results
Following extensive analysis of the nine alternatives that came out of the scoping meetings last March, the Expo Authority has narrowed down the routes and modes that will move forward through the environmental process for further analysis. These include Light Rail Transit (LRT) on the Exposition Right-of-Way (ROW) and LRT on Venice/Sepulveda (then connecting with the ROW). In addition, Transportation Systems Management improvements and a No-Build option will also be evaluated.
Project Process and Schedule
Project Kickoff and Public Scoping
Definition of AA/DEIS/DEIR Alternatives
Public Comment on DEIS/DEIR
Adoption of Locally Preferred Alternative
Circulation of FESI/FEIR
Begin Construction
Begin Service
Winter 2007
Fall 2007
Fall 2008
Winter 2009
Fall 2009
2010
2014-2015